Mariam's answer to Bryan's Secondary 4 E Maths Singapore question.
done
{{ upvoteCount }} Upvotes
clear
{{ downvoteCount * -1 }} Downvotes
Since 5 men require 84hrs to complete the job,
1 men will require 420hrs to complete the job and 6 men will require only 70 hrs to complete the job. 70hrs for 7 days so 10hrs per day.
1 men will require 420hrs to complete the job and 6 men will require only 70 hrs to complete the job. 70hrs for 7 days so 10hrs per day.