5 men took 12 days to complete a task, 7 hours per day. How many hours per day would 6 men take if they are to complete the task in 7 days?

Date Posted: 3 years ago
Views: 207

See 1 Answer

done {{ upvoteCount }} Upvotes
clear {{ downvoteCount * -1 }} Downvotes
Mariam
Mariam's answer
5 answers (A Helpful Person)
1st
Since 5 men require 84hrs to complete the job,
1 men will require 420hrs to complete the job and 6 men will require only 70 hrs to complete the job. 70hrs for 7 days so 10hrs per day.