The number of workers is inversely proportional to the number of days taken. If 6 workers take 24 days, then 1 worker takes 144 days since the worker has to do 6 workers' worth of jobs.

Note that rates of work done (house per day) add up. For example, if you make 5 cakes per day and your friend makes 3 cakes per day, then the total is 8 cakes per day.

-------------------------------------------------------

Actually, the number of days it takes for 1 trained worker and 2 untrained workers to complete THE SAME house is 0 days, since the house has already been completed.

But the number of days it takes for 1 trained worker and 2 untrained workers to complete A SIMILAR house is 80 days.