ST's answer to Kc's Primary 6 Maths Data Analysis Singapore question.

done {{ upvoteCount }} Upvotes
clear {{ downvoteCount * -1 }} Downvotes
ST
St's answer
11 answers (Tutor Details)
1st
If 60 cleaners take 12 days to clean a school, then twice the number of cleaners will be needed to clean a school in half the time.

60 cleaners —> 12 days
120 cleaners —> 6 days
24 cleaners —> 30 days

30 days = 6 days x 5
So, the number of cleaners required to clean the school in 30 days = 120 cleaners divided by 5.