Question

primary 5 | Maths | Decimals
One Answer Below

Anyone can contribute an answer, even non-tutors.

Answer This Question
Choo
Choo

primary 5 chevron_right Maths chevron_right Decimals chevron_right Singapore

Please help with explanation. Thank you very much

Date Posted: 4 years ago
Views: 595
J
J
4 years ago
Each day, he paved 0.06km less than planned.

0.24 km - 0.06 km = 0.18 km
So he only paved 0.18 km a day.

In 12 days,

0.18 km x 12 = 2.16 km

He would have paved only 2.16 km

He still had 0.405 km of road not paved after 12 days. So he has 0.405 km more to pave.

Total length of road to pave
= 2.16 km + 0.405 km
= 2.565 km
Choo
Choo
4 years ago
Thank you very much

See 1 Answer

He plans to pave 0.24km in one day.
Everyday, he pave 0.06km less than what was plan.
So,
1 day, he pave 0.24km - 0.06km = 0.18km
After 12 days, he would pave 2.16km
0.18 x 12 = 2.16km
Total length of road = amount he paved + amount unpaved
Total length of road = 2.16 + 0.405 = 2.565km
done {{ upvoteCount }} Upvotes
clear {{ downvoteCount * -1 }} Downvotes
TIEW KAI JIE NICHOLAS
Tiew Kai Jie Nicholas's answer
107 answers (Tutor Details)
1st
Choo
Choo
4 years ago
Thank you very much
Choo
Choo
4 years ago
Thank you