Ask Singapore Homework?
Upload a photo of a Singapore homework and someone will email you the solution for free.
Question
Secondary 1 | Maths
2 Answers Below
Anyone can contribute an answer, even non-tutors.
hi , pls kindly advise which method is correct , thanks
Usually I would just skip the 12 man-hours and just do multiplication and division.
So here it would be 12 man-hours as the total time and not 12 hours.
So, if a building is to be completed by two people, they share the workload so that each person does half the building, but as a whole, the same proportion of building is completed.
So a homework which is two pages long can be thought of as to be completed in a single person by 2 hours. We call this “man-hours”, the overall total time spent by each of the students as a whole, but this remains unchanged.
Two person who share the same homework, and thus complete one page each, contributes to a total of 2 man-hours of work (1 man-hour from each person because each person only completes one page of homework).
Assuming the men have the same productivity and efficiency/work-rate ,
If 2 men take 6 hours each to build the car,
Then each man builds ½ the car in 6 hours.
In 1 hour,
½ x 1/6 = 1/12
Each man builds 1/12 of the car in 1 hour.
For 3 men,
1/12 x 3 = 3/12 = 1/4
3 men build 1/4 of the car in 1 hour.
So they will need 4 hours each to build the whole car.
Then 1 man would need 24 hours to complete the whole car if he worked alone.
But that is not correct as 1 man can complete ½ the car in 6 hours. So he'll only need 12 hours in total to build the whole car
Method 3 cannot work as you could then also write 1 man : 12 hours total
So we can't multiply and divide in a similar fashion to method 2.
So if 50000 people work together, for 1 hour in the same time, 50000 man-hours have elapsed. But in reality only 1 hour has passed.
See 2 Answers
For this question, it says 2 men works 6 hours each.
So isn't it right to say:
1 man works 6 hours and so
3 men will also work 6 hours each?