can someone please help me? the answer is 7.5 days but idk how please help!!

Date Posted: 5 years ago
Views: 331
J
J
5 years ago
4 workers , 80 chairs, 12 days

24 workers → 6 times the manpower

So 80 chairs x 6 = 480 chairs in 12 days

To manufacture 300 chairs,

300 ÷ 480 = 5/8

so 5/8 of 12 days = 7.5 days is needed.

See 1 Answer

done {{ upvoteCount }} Upvotes
clear {{ downvoteCount * -1 }} Downvotes
Eric Nicholas K
Eric Nicholas K's answer
5997 answers (Tutor Details)
1st
The three cases you need to know:

1. Same amount of time means more workers can produce more chairs.

2. Same number of workers means more time is needed to produce more chairs.

3. Same number of chairs produced means more workers need less time altogether.