Hi, need need on this question. Tks.
So 2 workers can paint 2 houses in 2 days.
Now, 6 workers is 3 times of 2 workers.
So they will be 3 times as fast. This also means they will take ⅓ of the time.
Number of days 6 workers will take to paint 2 houses
= 2 days ÷ 3
= ⅔ day