Ask Singapore Homework?

Upload a photo of a Singapore homework and someone will email you the solution for free.



Question

primary 5 | Maths | Rate & Ratio
2 Answers Below

Anyone can contribute an answer, even non-tutors.

Answer This Question
Ashton
Ashton

primary 5 chevron_right Maths chevron_right Rate & Ratio chevron_right Singapore

Can anyone help. Thank you so much.

Date Posted: 1 year ago
Views: 271
AC Lim
AC Lim
1 year ago
Let the job = 240u, 1 man =1u per day
5 men → 240u →48 days
6 men → 240u →40 days
8 men → 240u →30 days
10 men → 240u →24 days
12 men → 240u → 20 days.

Therefore, 12 men reduced 48-20 = 28 days.
Need another 7 men.

See 2 Answers

done {{ upvoteCount }} Upvotes
clear {{ downvoteCount * -1 }} Downvotes
AC Lim
Ac Lim's answer
13086 answers (A Helpful Person)
1st
Hope this helps ♦
done {{ upvoteCount }} Upvotes
clear {{ downvoteCount * -1 }} Downvotes
Xavier Sng
Xavier Sng's answer
801 answers (A Helpful Person)
Using the concept of workload represented by the number of workers multiplied by the number of days, this becomes a very quick way to derive the answer. Hope it helps. Regards